A reminder that the following out-of-hours works will be carried out this week, subject to weather and site conditions:

Temporary acoustic shed at Hickson Road, Millers Point

8pm to 5am Monday 16 April - acoustic shed construction, installing walls, delivery of steel columns and framework
8pm to 5 am Tuesday 17 April - acoustic shed construction, installing walls, deliveries of steel columns and framework
8pm to 5am Wednesday 18 April - acoustic shed construction, installing walls, deliveries of steel columns, framework and gantry crane rails.

Utility relocations at Hickson Road, Millers Point (near Nawi Cove)

8pm to 5am Monday 16 April - relocating underground water main
8pm to 5 am Tuesday 17 April - relocating underground water main
8pm to 5am Wednesday 18 April - relocating underground water main.

Utility relocations at corner of Sussex Street and Erskine Street

8pm to 5am Tuesday 17 April - relocating underground electrical main
8pm to 5am Wednesday 18 April - relocating underground electrical main
8pm to 5am Thursday 19 April - relocating underground electrical main.

These works must be done at night when traffic volumes are low and to ensure public safety. Some temporary single lane road closures will be in place while this work is carried out. Every effort will be made to keep noise to a minimum and high-noise activities will be completed before midnight. There will be no impact to water or electrical services during these works. 

Please see the attached notification for more information.

If you have any questions, please contact our team on 1800 171 386 or at This email address is being protected from spambots. You need JavaScript enabled to view it..